VLBI Broad Band Development Memo Series
![]()
| 007 | 111307 | X1_experiment_plan (Wfrd circular) |
A.E. Niell | |
| 008 | 060908 | Using the DBE1 and Mk5B+ with merged IF0 and IF1 (geodesy) |
A.E. Niell | |
| 051108 | Spurious Signals at MV3 | A.Niell |
||
| 061108 | Surious Signal test in DBEI | A.Niell |
||
| 042508 | Results of Westford Dewar Y Factor Measurements | C. Beaudoin |
et al. |
|
| 050208 | GGAO Receive Chain Component Configuration Considerations | C. Beaudoin |
||
| 017 | 062508 | Modification to NASA/Honeywell pcal for 5 MHz repetition rate |
A.E.E. Rogers | |
| 018 | 070808 | GPIB over Ethernet capability, system temperature, and LNA status at MV3 |
C. Beaudoin |
|
| 019 | 060808 | Preliminary analysis of correlator data from 2008 May 23 GGAO-Westford BBD test | B. Corey | |
| 020 | 061008 | Modulation during first hour of 2008 May 23 GGAO-Westford BBD test | B. Corey | |
| 021 | 061208 | Phase cal performance during 2008 May 23 GGAO-Westford BBD test | B. Corey | |
| 022 | 061508 | Addendum to June 10 memo on “Modulation during first hour of 2008 May 23 GGAO-Westford BBD test” | B. Corey | |
| 023 | 080608 | Preliminary test of new “digital” phase calibrator | A.E.E. Rogers | |
| 024 | 082708 | New scripts and utilities for DBE1 setup and diagnostics | C.Beudoin |